topbar

Projects


Thumbnails: Click for a larger image

Murphy International

Location: Ballymoney, Northern Ireland.
Job Description: Installed 240 metres of 6” steel pipe for the Northwest Pipeline beneath the river Bann.
Drilling Method: Wireline tracking with mud motor and rock roller bits. Working Depth was 13 metres.
Ground Conditions: Rock and bolder clay



Thumbnails: Click for a larger image

McAvoy Construction Ltd

Location: Dundalk, County Louth.
Job Description: Supplied and installed 190 metres of 560mm duct for a pumping main beneath two roads gardens and buildings.  Working depth was 8.4 metres.
Drilling Method: Jetting assembly and fly cutters
Ground Conditions: Running sands and silts, saline intrusion.

 


Thumbnails: Click for a larger image

Tristway Ltd.

Location: Arklow, County Wicklow.
Job Description: Supplied and installed 150 metres of 315mm duct from land to sea for the power cable coming from the off-shore wind farm.  Working depth of 15.4 metres beneath the sea bed.
Drilling Method: Wireline tracking with jetting head and aggressive fluted reamers.
Ground Conditions: Running sands/gravels, peat and clay.

 


Thumbnails: Click for a larger image

B. Mullan & Sons Ltd.

Location: Limavady, County Derry.
Job Description: Supplied and installed 170 metres of 250mm foul sewer to a grade of 1.0 percent  beneath a SSSI site.  Working depth of 7.0 metres.
Drilling Method: Jetting assembly and fluted reamers
Ground Conditions: Running sands/gravels, and clay.